Back to insights

    Series ยท 10 parts

    Delay and Disruption Costs, Loss and Expense: A 10-Part Guide

    Time overruns are almost universal on major projects. Whether the project is a metro extension, a utility-scale solar plant, a desalination facility, a high-rise tower or a remote resources camp, the commercial consequences of lateness and lost productivity regularly become the largest numbers in the dispute.

    Yet the quantum of delay and disruption is where many otherwise well-founded claims fail. Tribunals are rarely persuaded by a number on its own. They want to see the entitlement, the causal chain, the period, the resources affected, and the records that prove the money was actually spent.

    This series sets out how a quantum expert approaches that task, step by step.

    PartTitleCore question
    1Delay Is Not Disruption: Why the Distinction Decides the ClaimIs this a time claim, a productivity claim, or both?
    2Entitlement Before Quantum: The Basis of RecoveryUnder what mechanism, and on what valuation basis, is the claim made?
    3Mapping the Heads of ClaimWhat categories of loss could be in play?
    4Labour Costs Under DelayHow does delay change what the workforce costs?
    5Time-Related Preliminaries: Proving Actual CostWhat did it actually cost to keep the site running longer?
    6When the Contract Sets the Price: Valuation Other Than CostWhen do rates, not ledgers, govern the answer?
    7Which Period? Assessing Prolongation When the Effect Was FeltWhen were the extra costs actually incurred?
    8Overheads, Profit, Finance and Lost ProductionWhat sits beyond site-level cost?
    9Concurrency, Global Claims and the Causal LinkWhat happens when more than one cause is at work?
    10Proven, Estimated or Speculative: The Expert's Evidential DisciplineHow much weight can the number bear?

    A note on jurisdiction. Much of the leading authority on delay quantum comes from England, Scotland and other common law jurisdictions. In the UAE and wider GCC, those decisions are not binding, but they are frequently cited as persuasive in arbitration (including under DIAC and arbitrateAD rules) and in the DIFC Courts, and they shape how international experts and tribunals think. Where the UAE Civil Code or another civil law regime governs, the legal test for compensation must be confirmed by qualified local counsel. This series addresses the quantum methodology; it is not legal advice.

    All parts in the series