Cost and Time

    DIAC 2024 Annual Report: Construction Disputes Still Dominate Dubai Arbitration

    DIAC registered 295 cases in 2024, with construction and real estate accounting for 58% of the caseload. What the figures mean for parties appointing construction expert witnesses.

    By Garry Andrews3 min read
    • DIAC
    • arbitrateAD
    • SCCA
    • QICCA
    • BCDR
    • DIFC Courts
    • ADGM Courts
    • QICDRC
    • BICC

    The Dubai International Arbitration Centre (DIAC) published its Annual Report for 2024, and for anyone advising on construction disputes in the UAE the headline is unmistakeable: construction remains the engine room of Dubai arbitration. Of the cases administered by the Centre in 2024, disputes in the construction and real estate sector represented 58% of the total caseload โ€” almost three in every five arbitrations.

    DIAC registered 295 cases in 2024, comprising 262 administered arbitrations and 33 appointing authority cases. While that is down from 355 cases in 2023, it marked the third consecutive year in which the Centre registered more than 250 administered arbitrations, and the Centre has now administered more than 1,300 arbitrations over five years. Volume has stabilised at a materially higher level than the pre-2022 era.

    Construction and Real Estate: 153 Cases

    The sector breakdown records 153 construction and real estate disputes, with commercial and residential construction leading, followed by real estate development. Energy accounted for 26 cases (around 10%), overtaking banking and finance, with retail and consumer goods (20), transport and logistics (19) and manufacturing and industrial (14) following behind.

    Looked at by contract type rather than sector, construction contracts were the most common underlying agreement, accounting for 107 cases or 41% of all administered arbitrations โ€” consistent with 40% in 2023. Sale and purchase contracts rose sharply to 66 cases (25%), with service and provider contracts at 31 and real estate and property contracts at 16.

    Why This Matters When Appointing an Expert Witness

    A caseload weighted this heavily towards construction has practical consequences. DIAC tribunals are, as a body, highly experienced in the technical vocabulary of construction claims โ€” critical path analysis, measured mile studies, prolongation cost, defect root-cause investigation and FIDIC contract mechanics. Expert evidence that is generic, under-evidenced or methodologically loose is unlikely to survive that scrutiny.

    It also means construction experts appearing before DIAC tribunals should be fluent in the procedural architecture of the DIAC Arbitration Rules 2022, which govern how, when and in what form expert evidence is delivered. Directions on expert reports, expert conferencing, joint statements and hearing procedure all flow from the tribunal's powers under those Rules and the procedural timetable set at the first case management conference.

    Younger Contracts, Faster Disputes

    One of the more striking statistics is the age of the underlying agreements. Some 71% of the contracts in dispute were concluded within the previous six years, and more than 36% arose from contracts concluded between 2022 and 2024 โ€” up sharply from 25% the previous year. Disputes are reaching arbitration faster after contract award.

    For contractors and employers this compresses the record-keeping window that matters. Where a dispute can crystallise within two or three years of signature, contemporaneous records โ€” programme updates, site instructions, delay notices, cost allocations and defect inspection reports โ€” need to be maintained to evidential standard from day one, not reconstructed later under time pressure.

    What Parties Should Take From the 2024 Figures

    Three practical points follow. First, if you are contracting in Dubai in the construction, real estate or energy sectors, the realistic dispute forum is DIAC arbitration, and your contract administration should be built with that in mind. Second, expert evidence is central rather than peripheral in this caseload โ€” quantum, delay and defects experts should be engaged early enough to shape record-keeping and case strategy. Third, the growing average value in dispute means the cost of weak evidence has risen materially.

    Our experts act as quantum, delay, defects and structural expert witnesses in DIAC arbitrations and DIFC Court proceedings across the UAE and wider Middle East, preparing reports and giving oral evidence to the standards those forums expect.

    Frequently asked questions

    Sources & further reading

    Who we work with

    For lawyers and in-house counsel

    Independent, tribunal-ready evidence that maps to the pleadings and the list of issues, with early sight of evidential gaps.

    Discuss an instruction

    For contractors and engineering firms

    Understand what a claim is really worth before you commit โ€” and independent evidence that stands up to scrutiny if it proceeds.

    Talk to us about a claim

    For private clients and developers

    Plain-language advice on where the real exposure lies, and a clear basis for settlement or the next stage of the dispute.

    Arrange a confidential call

    Need a construction expert witness?

    Tell us about the dispute, the forum and the timetable. We'll complete a conflict check and come back to you promptly.

    Discuss an instruction

    Please do not send confidential documents until a conflict check has been completed.