International construction arbitration is, by design, a meeting point of legal traditions. A DIAC tribunal seated in Dubai may comprise a common law-trained chair, a civil law-trained co-arbitrator, and counsel drawn from both traditions representing an employer and a contractor headquartered in yet different jurisdictions. Understanding how these traditions diverge on the taking of evidence โ and how that divergence is increasingly bridged in practice โ is essential to running an efficient and persuasive construction case.
Document Production: A Point of Genuine Divergence
The clearest fault line lies in document disclosure. Common law practitioners tend to arrive expecting a disclosure phase resembling, even in attenuated form, the discovery process familiar from litigation โ broad categories of documents, met with resistance, refined through a Redfern Schedule. Civil law practitioners, by contrast, are often trained in a tradition where each party proves its own case from documents already in its possession, and where compelled production of an opponent's documents is the exception rather than the norm. In a construction dispute, this matters enormously: delay and disruption claims frequently depend on internal contemporaneous records โ daily diaries, resource allocation sheets, internal correspondence โ that only the opposing party holds. A tribunal's approach to document production requests can materially determine whether such evidence ever reaches the record.
Witness and Expert Evidence: Converging Practice
Civil law systems traditionally place less weight on witness testimony generally, and treat party-appointed experts with more institutional suspicion than common law systems, which have developed detailed procedural machinery โ cross-examination, expert conferencing, Daubert-style scrutiny in some jurisdictions โ for testing expert opinion. In construction arbitration, however, practice has substantially converged: written witness statements and written expert reports, exchanged in advance and tested through structured cross-examination or tribunal-led questioning at a hearing, are now close to universal regardless of the arbitrators' legal training. The IBA Rules on the Taking of Evidence have been a significant driver of this convergence, offering a hybrid procedure deliberately designed to be acceptable to both traditions.
Standard of Proof
Civil law and common law jurisdictions also differ, at a conceptual level, in how they articulate the standard of proof applicable to disputed facts โ a question addressed in more detail later in this series in the specific context of quantum evidence. For construction disputes, where causation questions (was a particular delay event critical to completion; did a particular design deficiency cause a particular defect) are rarely susceptible of certainty, the tribunal's approach to weighing competing expert narratives against a stated standard of proof has a direct bearing on outcome.
Practical Implications for UAE-Seated Construction Arbitration
DIAC tribunals, drawing on a genuinely international pool of arbitrators, generally adopt a pragmatic middle path: some document production consistent with IBA Rules principles, written witness and expert evidence tested at an oral hearing, and cost-conscious case management reflecting Prague Rules-influenced efficiency thinking without abandoning common law-style evidentiary testing altogether. For parties and their experts, the practical lesson is not to assume either a common law or a civil law approach by default, but to establish the tribunal's evidentiary preferences early โ ideally at the first case management conference โ and to tailor the scope and format of expert evidence accordingly, particularly given how directly this affects the cost and timeline issues explored elsewhere in this series.