The single procedural decision with the greatest influence on the cost and duration of a construction arbitration is not made at the hearing โ it is made at the first case management conference, when the tribunal and parties agree the framework for document production, witness and expert evidence, and hearing structure. Getting this framework right, tailored to the specific evidentiary demands of a construction dispute, pays dividends throughout the case.
Sequencing Document Production Around the Technical Case
Rather than treating document production as a generic phase preceding witness statements, an efficient construction procedure sequences it around the specific delay, disruption, or quantum methodology the experts will apply. If a delay expert intends to run a time-impact analysis keyed to specific programme revisions, the document production phase should be scoped to secure those revisions and their supporting records before the expert's analysis is finalised โ not after, when late-produced documents risk requiring a costly re-analysis.
Bifurcation and Phased Procedures
For disputes combining liability, causation, and quantum issues, bifurcation โ resolving liability first, with quantum evidence deferred pending the outcome โ can avoid the cost of a full quantum expert exercise on claims that may not survive a liability determination. This is a particularly relevant tool in construction disputes involving multiple, discrete claim heads (variations, delay, defects, prolongation) where liability findings on some heads may resolve or substantially narrow the case before quantum evidence needs to be finalised on all of them.
Structuring Expert Evidence Exchange
A well-planned procedural timetable typically provides for simultaneous or sequential exchange of expert reports (simultaneous exchange is more common where independence is a live concern), followed by a joint expert conferencing process producing a joint statement identifying agreed and disputed issues, and only then proceeding to a hearing focused specifically on the matters the joint statement identifies as genuinely contested. This sequencing โ increasingly standard in DIAC construction references โ prevents hearing time being spent on issues the experts in fact agree upon.
Managing Multiple Expert Disciplines in Parallel
Complex construction disputes frequently require delay, quantum, and technical (structural, geotechnical, or MEP) experts to work in parallel, with each discipline's conclusions feeding into the others โ a quantum expert's prolongation costs calculation, for example, depends on the delay expert's critical path findings. The procedural timetable should account for this interdependency explicitly, sequencing report exchange so that quantum reports can properly incorporate delay findings rather than being prepared on a provisional or assumed basis that then requires revision.
Setting Realistic Hearing Time
Construction hearings are frequently under-timetabled relative to the volume of expert evidence involved. Agreeing hearing time allocation per witness and expert at the procedural order stage โ informed by a realistic view of how many issues genuinely require oral testing after the joint statement process โ reduces the risk of a rushed, compressed hearing that limits the tribunal's ability to properly test competing expert evidence on technically dense issues.