    How to Record and Prove a Disruption Claim

    A guide to capturing the records that make disruption claims provable, and to the measured mile and other accepted methods of demonstrating lost productivity.

    By Garry Andrews1 min read
    • DIAC
    • arbitrateAD
    • SCCA
    • QICCA
    • BCDR
    • DIFC Courts
    • ADGM Courts
    • QICDRC
    • BICC

    Disruption claims fail more often than delay claims, and almost always for the same reason: the records were never kept in a form that allows productivity loss to be measured. This guide explains what to capture and how to analyse it.

    Understand what disruption is

    Disruption is the loss of productivity or efficiency in carrying out the works. It is distinct from delay: work can be disrupted and still finish on time, at greater cost. Entitlement usually arises from breach, variation, or a contractual mechanism for loss and expense.

    Capture the right records from day one

    • Daily labour allocation by activity and location, not just headcount on site.
    • Plant utilisation records.
    • Quantities installed per period, by activity.
    • Instructions, variations, and access or information constraints, dated.
    • Photographs and drone surveys tied to dates and locations.

    Choose an analysis method

    Measured mile

    Compare productivity in an unimpacted period against the impacted period for the same activity and crew type. Where a genuinely comparable baseline period exists, this is the most persuasive approach.

    Earned value and baseline comparisons

    Where no clean period exists, compare achieved productivity against tender allowances or industry benchmarks. Expect this to be tested hard, so document why the baseline is reasonable.

    Modelling approaches

    System dynamics and study based factors can support a claim but should be corroborated by project records rather than used alone.

    Quantify carefully

    Convert lost hours into cost using evidenced rates, then check the total against the project's actual cost overrun. If the claim exceeds the overrun, the analysis needs revisiting before it reaches a tribunal.

    Who we work with

    For lawyers and in-house counsel

    Independent, tribunal-ready evidence that maps to the pleadings and the list of issues, with early sight of evidential gaps.

    Discuss an instruction

    For contractors and engineering firms

    Understand what a claim is really worth before you commit โ€” and independent evidence that stands up to scrutiny if it proceeds.

    Talk to us about a claim

    For private clients and developers

    Plain-language advice on where the real exposure lies, and a clear basis for settlement or the next stage of the dispute.

    Arrange a confidential call

    Need a construction expert witness?

    Tell us about the dispute, the forum and the timetable. We'll complete a conflict check and come back to you promptly.

    Discuss an instruction

    Please do not send confidential documents until a conflict check has been completed.