Disruption claims fail more often than delay claims, and almost always for the same reason: the records were never kept in a form that allows productivity loss to be measured. This guide explains what to capture and how to analyse it.
Understand what disruption is
Disruption is the loss of productivity or efficiency in carrying out the works. It is distinct from delay: work can be disrupted and still finish on time, at greater cost. Entitlement usually arises from breach, variation, or a contractual mechanism for loss and expense.
Capture the right records from day one
- Daily labour allocation by activity and location, not just headcount on site.
- Plant utilisation records.
- Quantities installed per period, by activity.
- Instructions, variations, and access or information constraints, dated.
- Photographs and drone surveys tied to dates and locations.
Choose an analysis method
Measured mile
Compare productivity in an unimpacted period against the impacted period for the same activity and crew type. Where a genuinely comparable baseline period exists, this is the most persuasive approach.
Earned value and baseline comparisons
Where no clean period exists, compare achieved productivity against tender allowances or industry benchmarks. Expect this to be tested hard, so document why the baseline is reasonable.
Modelling approaches
System dynamics and study based factors can support a claim but should be corroborated by project records rather than used alone.
Link cause to effect
Identify each disruptive event, the activities it touched, the period affected, and the measured productivity loss for those activities. A schedule mapping events to affected work packages is far more convincing than a narrative followed by a single lump sum.
Quantify carefully
Convert lost hours into cost using evidenced rates, then check the total against the project's actual cost overrun. If the claim exceeds the overrun, the analysis needs revisiting before it reaches a tribunal.