A quantum expert's task is to answer a simple sounding question โ how much? โ using evidence that can be traced, tested and reconciled. This guide explains how to prepare so that the report is built on solid ground.
Gather the primary cost record
- Contract, bills of quantities, and priced schedules.
- Payment applications, certificates and payment records.
- Subcontract and supply orders, invoices and variation accounts.
- Labour timesheets and plant hire records.
- The project cost ledger, exported at a level that allows reconciliation.
Value variations under the contract first
Most forms set an order of precedence: contract rates where the work is of similar character and conditions, pro-rata rates where it is similar but not identical, then fair valuation. Departing from that order without explanation invites challenge.
Treat prolongation cost properly
Prolongation cost is the time-related cost actually incurred during the period of compensable delay. It is assessed for the period in which the delay occurred, using actual records, rather than by applying a tender preliminaries rate across the extension.
Address loss and expense heads separately
Site overheads, head office overheads, finance cost, disruption, and loss of profit each require distinct evidence. Formulae for head office overhead are a last resort where direct evidence is unavailable and should be justified.
Reconcile and sense-check
Reconcile the sum claimed to the audited or ledger cost, deduct amounts already certified, and remove duplication between heads of claim. Overlap between disruption and prolongation is the most frequent double count.
Present the numbers so they can be followed
Build the report so that any figure can be traced from the summary table, through the calculation, to the source document. Where assumptions are needed, state them and show the sensitivity of the result to each one.