    How to Prepare an Extension of Time Claim: A Step-by-Step Guide

    A practical, step-by-step guide to preparing a defensible extension of time claim under FIDIC and UAE construction contracts, from notice to delay analysis and submission.

    By Garry Andrews3 min read
    • DIAC
    • arbitrateAD
    • SCCA
    • QICCA
    • BCDR
    • DIFC Courts
    • ADGM Courts
    • QICDRC
    • BICC

    An extension of time (EOT) claim is not simply a request for more time. It is a contractual entitlement that must be established on evidence: a qualifying event, proper notice, a demonstrable effect on the critical path, and a resulting delay to a contractual completion date. This guide sets out how to build that case step by step.

    Step 1: Identify the qualifying event

    Start with the contract. Under FIDIC based forms widely used across the UAE and wider GCC, entitlement flows from specified events such as variations, employer delays, exceptionally adverse climatic conditions, unforeseeable physical conditions, or delays caused by authorities. Record the clause number that gives entitlement and the exact date the event arose.

    Step 2: Serve notice within the time bar

    Most standard forms impose a strict notice period, often 28 days from when the contractor became aware, or should have become aware, of the event. Treat this as an absolute deadline. The notice should identify the event, the clause relied upon, and state that further particulars will follow.

    • Send notice in the contractual manner and to the contractual address.
    • Keep proof of transmission and receipt.
    • Follow up with detailed particulars within the period the contract requires.

    Step 3: Assemble contemporaneous records

    Expert evidence is only as strong as the records behind it. Gather the baseline programme, progress updates, site diaries, labour and plant allocation sheets, minutes of meetings, correspondence, instructions, requests for information, and inspection records.

    Step 4: Establish the delay using an appropriate method

    The Society of Construction Law Delay and Disruption Protocol describes several accepted approaches. The method should be chosen on the basis of the records available, the contract, and the stage at which the claim is being made.

    Prospective methods

    Impacted as-planned and time impact analysis model the likely effect of an event on the programme. These suit contemporaneous assessment during the works.

    Retrospective methods

    As-planned versus as-built, windows analysis and collapsed as-built examine what actually happened. These suit claims prepared after completion when as-built records exist.

    Step 5: Prove causation and concurrency

    Establishing that an event occurred is not enough. You must show that it affected the critical path and delayed a contractual completion date. Where employer and contractor delays overlap, address concurrency openly and explain the approach taken, because the tribunal will test it.

    Step 6: Quantify the time, then the money

    An EOT claim relieves liability for delay damages and opens the door to prolongation cost. Keep the time case and the money case separate and consistent โ€” the prolongation period must match the extension granted, and costs must be evidenced for that period.

    Step 7: Present the claim clearly

    A strong submission has a short executive summary, a chronology, the contractual basis, the factual narrative supported by document references, the delay analysis, and clearly stated relief sought. Appendices should be indexed so that a reviewer can find any cited document quickly.

    Common reasons EOT claims fail

    • Notice served late or in the wrong form.
    • Reliance on a programme that was never agreed or was not a realistic baseline.
    • Delay analysis that ignores contractor culpable delay.
    • Global claims with no attempt to link cause and effect.
    • Costs claimed for a period that does not match the delay demonstrated.

    Who we work with

    For lawyers and in-house counsel

    Independent, tribunal-ready evidence that maps to the pleadings and the list of issues, with early sight of evidential gaps.

    Discuss an instruction

    For contractors and engineering firms

    Understand what a claim is really worth before you commit โ€” and independent evidence that stands up to scrutiny if it proceeds.

    Talk to us about a claim

    For private clients and developers

    Plain-language advice on where the real exposure lies, and a clear basis for settlement or the next stage of the dispute.

    Arrange a confidential call

    Need a construction expert witness?

    Tell us about the dispute, the forum and the timetable. We'll complete a conflict check and come back to you promptly.

    Discuss an instruction

    Please do not send confidential documents until a conflict check has been completed.