Defect disputes turn on causation. A structured investigation makes the difference between an opinion that persuades and one that is dismissed as assertion.
Define the scope before attending site
Establish what is alleged, where, and since when. Obtain the design drawings, specification, as-built information, material approvals, inspection and test plans, handover documents and maintenance records.
Conduct a staged inspection
Stage one: visual and non-destructive
Record conditions systematically by location with photographs, moisture readings, thermography, cover meter surveys and crack mapping. Establish the pattern and distribution of the defect.
Stage two: opening up and testing
Agree an opening-up protocol with the parties, including notice, joint attendance and reinstatement. Sample and test to recognised standards, and preserve samples with a documented chain of custody.
Analyse the root cause
Distinguish between design inadequacy, non-compliant materials, defective workmanship, inadequate maintenance and normal wear. In the GCC, consider the specific drivers of failure: sustained high temperatures, high humidity and salt-laden air, chloride and sulphate attack on concrete, thermal cycling of facades and roofing, and water ingress at interfaces.
Establish compliance
Compare what was built against the contract specification and the applicable codes and authority requirements. Non-compliance and defect are related but not identical, and the distinction matters to liability.
Assess the remedy and its cost
Identify the reasonable scheme of repair, not the most expensive one. Consider betterment, temporary works, decanting and business interruption, and confirm whether the remedy must address the cause or only the symptom to be effective over the design life.
Report so it can be tested
Set out the facts observed, the tests performed and their results, the opinions reached, the reasoning connecting the two, and any matters on which further information would change the conclusion.