Pillar guide ยท Part 17 of 20

    Evidencing Force Majeure and Changed Circumstances in Construction Contracts

    Force majeure and changed circumstances claims have become significantly more prominent in construction disputes since 2020, driven by pandemic-related disruption, supply chain volatility, and regional geopolitical events affecting materials and logistics.

    By Garry Andrews3 min read
    • DIAC
    • arbitrateAD
    • SCCA
    • QICCA
    • BCDR
    • DIFC Courts
    • ADGM Courts
    • QICDRC
    • BICC

    Force majeure and changed circumstances claims have become significantly more prominent in construction disputes since 2020, driven by pandemic-related disruption, supply chain volatility, and regional geopolitical events affecting materials and logistics. Successfully evidencing such a claim requires a materially different evidentiary approach than a conventional delay or quantum claim, because the party asserting force majeure or changed circumstances must prove both the triggering event and its specific causal impact on the contract's performance.

    The Contractual Threshold Under FIDIC and UAE Law

    Most major regional construction contracts are based on, or heavily influenced by, the FIDIC suite, which defines force majeure (in earlier editions) or exceptional events (in the 2017 Rainbow Suite) with specific criteria: the event must be beyond the affected party's control, could not reasonably have been provided for at the time of contracting, and its effects could not reasonably have been avoided or overcome. UAE Civil Code provisions on force majeure and, separately, on the doctrine allowing adjustment of contractual obligations rendered exceptionally onerous by unforeseen circumstances (a concept with particular relevance under Article 249 of the Civil Code) provide an overlapping, but not identical, statutory framework that a tribunal seated in the UAE will typically consider alongside the contractual force majeure clause itself.

    Evidencing the Triggering Event

    The first evidentiary burden is establishing that the claimed event actually occurred and falls within the contractual or statutory definition relied upon โ€” a matter usually proven through a combination of publicly available evidence (government orders, published indices, industry data) and project-specific evidence showing how the event manifested on the particular project in question. For pandemic-related claims specifically, government movement restriction orders, site access logs, and workforce mobilisation records have typically formed the core of this evidentiary record.

    Evidencing Causation and Impact

    The more evidentially demanding task is establishing the causal link between the triggering event and the specific delay, cost, or performance impact claimed โ€” a task that typically falls to the delay expert (for time impact) and the quantum expert (for cost impact) working from the same underlying factual record. A bare assertion that "the pandemic caused delay" is rarely sufficient; tribunals generally expect a reasoned, activity-level analysis showing which specific critical path activities were affected, by how much, and why the causal chain from the triggering event to the claimed delay is more likely than not established, consistent with the standards of proof discussed earlier in this series.

    Mitigation Evidence

    Because most force majeure and changed circumstances clauses (and the equivalent statutory doctrines) require the affected party to have taken reasonable steps to mitigate the impact, contemporaneous evidence of mitigation efforts โ€” alternative sourcing attempts, workforce reorganisation, sequence resequencing โ€” is frequently as important to the claim's success as evidence of the triggering event itself. Parties who fail to contemporaneously document mitigation efforts often find themselves reconstructing this evidence after the fact, a less persuasive exercise than a genuine contemporaneous record.

    Expert Coordination

    Given the layered evidentiary burden involved โ€” factual proof of the event, expert proof of delay causation, expert proof of cost impact, and evidence of mitigation โ€” force majeure and changed circumstances claims benefit particularly from close coordination between factual witnesses, delay experts, and quantum experts from the earliest stage of claim preparation, rather than each element being developed in isolation.

    ---

    This article is provided for general informational purposes and does not constitute legal advice.

    Who we work with

    For lawyers and in-house counsel

    Independent, tribunal-ready evidence that maps to the pleadings and the list of issues, with early sight of evidential gaps.

    Discuss an instruction

    For contractors and engineering firms

    Understand what a claim is really worth before you commit โ€” and independent evidence that stands up to scrutiny if it proceeds.

    Talk to us about a claim

    For private clients and developers

    Plain-language advice on where the real exposure lies, and a clear basis for settlement or the next stage of the dispute.

    Arrange a confidential call

    Need a construction expert witness?

    Tell us about the dispute, the forum and the timetable. We'll complete a conflict check and come back to you promptly.

    Discuss an instruction

    Please do not send confidential documents until a conflict check has been completed.