The DIAC Arbitration Rules 2022 introduced a package of procedural tools that materially changed how multi-party, multi-contract construction disputes are run in Dubai. DIAC's 2024 Annual Report gives the first substantial picture of how often those tools are actually used.
Emergency Arbitrators: Fast and Effective
DIAC received five applications for the appointment of an Emergency Arbitrator under Appendix II, Article 2 of the Rules in 2024, all made without notice to the respondent. In one case the Arbitration Court was not satisfied on a prima facie basis that emergency proceedings were justified and proceeded to constitute the tribunal instead. In the four that proceeded, the Emergency Arbitrator was appointed within one day of a complete application, and interim relief was granted in every one.
The timelines are notable: preliminary orders were issued the same day in one case, within 12 and 14 days in two others, and 35 days in a fourth where a virtual hearing was held and the timetable extended by consent. For construction disputes this matters where the relief sought concerns site access, preservation of works or records, calls on performance bonds, or preventing removal of plant.
Emergency relief compresses the expert's role severely. A delay or quantum expert supporting such an application may have days, not months. Practically, that means producing a focused, clearly caveated preliminary opinion on a defined question โ not a full report โ and being explicit about the limits of the material reviewed.
Joinder, Consolidation and Multi-Contract Claims
Parties applied to join a third party under Article 9 in five cases registered in 2024, up from four. Twelve requests for consolidation were made under Article 8.2, up from ten. Claims were brought under multiple contracts under Article 8.1 in 20 cases.
These provisions are tailor-made for construction. A single defect, delay or design failure typically implicates the employer, main contractor, subcontractor, and often the designer or supplier, across a chain of related agreements. Running those issues in separate arbitrations risks inconsistent findings on the same technical question.
Where consolidation or joinder succeeds, the expert's task changes character. A delay expert must analyse the critical path across contract packages rather than within one; a quantum expert must allocate cost and loss between multiple respondents and avoid double recovery. Both need a single, agreed programme and cost baseline spanning the consolidated proceedings โ building that baseline is often the largest single piece of work in the engagement.
Jurisdiction and Challenges
Respondents filed 16 preliminary jurisdictional objections under Article 6.2 in 2024, and the Arbitration Court determined prima facie jurisdiction in a further 34 cases. Four arbitrator challenges were received, of which two were upheld. DIAC attributes the rise in recorded jurisdictional objections partly to improved case management and data capture rather than a substantive surge.
Tribunal Composition and Timetable Pressure
The Arbitration Court constituted 242 tribunals in 2024 and appointed 388 arbitrators, a 170% increase in appointments year on year. Under Article 10.2 the default is a sole arbitrator absent party agreement, and 59% of tribunals were sole-arbitrator tribunals. Sole-arbitrator proceedings tend to move faster, which shortens the window for expert investigation โ another argument for instructing experts before, not after, the Request for Arbitration.
Practical Guidance for Construction Parties
Map the contract chain at the outset and decide early whether consolidation or joinder is being pursued, because it determines the scope of expert instructions. Preserve records across all packages, not just the one immediately in dispute. And if emergency relief is a realistic prospect, identify your expert before the trigger event, not on the day the application is drafted.
Our delay, quantum and defects experts work within these DIAC procedural mechanisms regularly, including in consolidated and multi-contract construction arbitrations seated in the DIFC and Dubai (outside the DIFC).