Construction contracts accounted for 107 of the arbitrations DIAC registered in 2024 — 41% of all underlying contracts — with commercial and residential construction the leading industries within the Centre's dominant construction and real estate sector. A substantial proportion of those disputes involve allegations of defective work, non-conforming materials, or failure to meet performance specifications.
Defect claims are evidentially distinct from delay and quantum claims. They turn on physical fact: what was built, what it should have been, why it failed, and what it will cost to put right. Before a DIAC tribunal, that chain has to be established with investigative rigour rather than assertion.
The Defects That Recur in the Gulf
The regional environment drives a recognisable pattern of failures. Waterproofing and tanking failures in basements and podium decks, exacerbated by aggressive saline groundwater. Façade and curtain wall problems including sealant degradation, thermal movement cracking and water ingress under driving rain. Concrete durability issues — chloride-induced reinforcement corrosion, thermal cracking in large pours, and inadequate cover. MEP shortfalls where installed chiller and HVAC capacity underperforms against design duty in peak summer conditions. And sand and dust ingress affecting mechanical plant, louvres and filtration.
Establishing Root Cause, Not Just Symptom
The central task of a building pathology expert is separating symptom from cause. Water staining on a ceiling slab is a symptom; the cause may be a failed waterproofing membrane, a defective joint detail, a services penetration sealed incorrectly, or a design that never accommodated the movement it experienced. Design defect, workmanship defect, material defect and maintenance failure each carry different contractual consequences and different responsible parties.
Credible root-cause work generally requires structured intrusive investigation: opening up representative locations, sampling and laboratory testing, and where appropriate non-destructive techniques such as thermography, cover meter surveys, half-cell potential testing and water penetration testing to recognised standards. Findings should be documented with photographs, sample locations and test certificates that another expert could independently verify.
Investigation Protocol and Preservation of Evidence
In DIAC arbitration, intrusive investigation frequently needs to be agreed between the parties or directed by the tribunal, particularly where the asset is occupied or where remedial works are already under way. Where remediation cannot wait, evidence preservation becomes critical — detailed photographic and video records, retained samples, and a witnessed record of conditions before the works proceed. Emergency relief under Appendix II to the DIAC Arbitration Rules 2022 is available where preservation of evidence genuinely cannot await tribunal constitution.
Quantifying the Remedy
Once causation is established, the quantum question follows: cost of repair, diminution in value, consequential losses such as loss of rent or business interruption, and any betterment deduction where the remedial scheme improves on the original specification. Defects experts and quantum experts should work from a single agreed remedial scope — a common failure mode is a technically sound defect report paired with a costing built on a different, broader scope of works.
Contract Mechanics and Limitation
Defect claims live within the contract's framework: the defects notification period and the employer's rights on expiry, decennial liability under the UAE Civil Code for structural failures, testing and taking-over provisions, and any contractual cap on liability. Under FIDIC forms the interaction between the defects notification period, performance certificate and continuing liability requires careful analysis, and the applicable governing law — UAE law in most DIAC cases, but English law in around 15% of 2024 cases — affects the answer.
Practical Guidance
Investigate early while the evidence is intact. Instruct a defects expert with regional experience of Gulf-specific failure mechanisms. Agree the investigation protocol with the other side where possible to reduce later argument about sampling bias. And align the technical and quantum evidence on a single remedial scope before either report is finalised.